passivhaus doesn't get Code 3 Sustainable homes - problem!
@ 28/01/09 – 19:39:24
-
comprison of Passivhaus and sap
@ 28/01/09 – 19:36:27
-
DCSF base costs 1Q2003
@ 23/01/09 – 10:59:38
DCSF base costs
Pubsec 144New School building £1,080/m²
Heavy refurb school building £750/m²
light refurb / refresh £150/m²
FF&E £1,000 / pupil
SEN FF&E £3,500/pupil
ICT infrastructure £225/pupil (no indexation)
ICT Equipment £1,450/pupil (no indexation)new build = 12% externals, 5% abnormals
refurb = 8% externals, 9% abnormalsfees 12.5% new, 15% refurb
-
DCSF Location factors January 2009
@ 22/01/09 – 10:13:11
http://www.teachernet.gov.uk/_doc/12295/DCSF_location_factors_Jan09.xls
should be used for DCSF projects
-
air permiable insulation from Scotland!
@ 17/01/09 – 09:27:04
http://www.building.co.uk/story.asp?sectioncode=748&storycode=3131374&c=1
seems like it could be good
-
Climate Safety report
@ 06/01/09 – 09:19:01